Shandong Business Delegation at BQIP on 24th Feb 2025

Shandong Business Delegation at BQIP PIDC and SIFC briefed the Business Delegation from Shandong, China on its visit to Bin Qasim Industrial Park (BQIP), an operational Special Economic Zone, developed and managed by PIDC. The Delegation was impressed by the availability of quality infrastructure at BQIP, and showed keen interest for future investment.  

Visit of Additional Secretary (Incharge), Ministry of Industries and Production to Master Changan Motor, Karachi (12th Oct, 2023)

Visit of Additional Secretary (Incharge), Ministry of Industries and Production to Master Changan Motor, Karachi (12th Oct, 2023) The Additional Secretary (Incharge) of Federal Ministry of Industries & Production Mr. Asad Rehman Gilani accompanied by Mr. Rizwan Ahmed Bhatti, CEO PIDC attended an event hosted by Master Changan Motor to celebrate its milestone of exporting […]

Inauguration of Rachna Industrial Park – Special Economic Zone by Honorable Federal Minister of Industries and Production Mr. Rana Tanveer Hussain on 20th May 2024

Inauguration of Rachna Industrial Park – Special Economic Zone by Honorable Federal Minister of Industries and Production Mr. Rana Tanveer Hussain on 20th May 2024 On 20th May 2024, the Honorable Federal Minister of Industries and Production Mr. Rana Tanveer Hussain inaugurated Rachna Industrial Park – Special Economic Zone, located in Sheikhupura, Punjab. The inauguration […]

Update on Under Construction 132Kv Grid Station at BQIP (06 Sep 2023)

Update on Under Construction 132Kv Grid Station at BQIP (06 Sep 2023) CEO PIDC visit to review the progress of ongoing construction work

Update on Under Construction 132Kv Grid Station at BQIP (04 Sep 2023)

Update on Under Construction 132Kv Grid Station at BQIP (04 Sep 2023) Concreate activity for the roof of Control House Building & Guard Room.

Update on Under Construction 132Kv Grid Station at BQIP (04 Sep 2023)

Update on Under Construction 132Kv Grid Station at BQIP (04 Sep 2023) Concreate pouring continued for roofing of Grid Station.

Update on Under Construction 132Kv Grid Station at BQIP (22 Jul 2023)

Update on Under Construction 132Kv Grid Station at BQIP (22 Jul 2023) A significant milestone of roof casting of the building to house Gas Insulated Switchgear (GIS) is achieved

Update on Under Construction 132Kv Grid Station at BQIP (3 May 2023)

Update on Under Construction 132Kv Grid Station at BQIP (3 May 2023) Joint Progress Review by PIDC Technical Dept. Project Consultant & Contractor.

Visit of Parliamentary Secretary on Industries & Production to Korangi Creek Industrial Park – Special Economic Zone (KCIP – SEZ), Karachi (2nd Jan 2023)

Visit of Parliamentary Secretary on Industries & Production to Korangi Creek Industrial Park – Special Economic Zone (KCIP – SEZ), Karachi (2nd Jan 2023) Previous Next • The Parliamentary Secretary on Industries & Production Ms. Shahida Rehmani visited KCIP – SEZ on 2nd Jan 2023. • During the visit of KCIP – SEZ, she also […]

Meeting of Federal Minister for Industries & Production with Industrialists of PIDC Managed SEZs in Karachi (12th Dec 2022)

Meeting of Federal Minister for Industries & Production with Industrialists of PIDC Managed SEZs in Karachi (12th Dec 2022) Previous Next • The Federal Minister for Industries & Production Mr. Syed Murtaza Mahmud accompanied by Mr. Rizwan Ahmed Bhatti, CEO PIDC met with industrialists of PIDC managed SEZs, i.e., Bin Qasim Industrial Park & Korangi […]